2012 Farm and Ranch Lands Protection Program --
Easement Process Flow Chart
*Contact
Ryan Dubois (for assistance opening
documents, as the website does not easily support non-PDF documents)

 
Step 1
The following constitutes a complete application package submitted by the
entity:
Step 3
NRCS
performs the
following tasks:
Step 2
NRCS
performs the following
tasks:
-
Verifies landowner and parcel eligibility
-
Reviews all
application information
-
Orders
AAI (Environmental Records Search)
 
If landowner or parcel is ineligible - STOP.
NRCS notifies entity of ineligibility.
 

If unfunded, eligible applicants receive
deferral letter at the end of fiscal year.





Step 4
NRCS performs the following tasks:
  
Step 6
Pre-Closing Continued
2 to 3 months prior to close
Entity submits the following documents within the requested time frame to
allow for NRCS review:
-
Baseline
(116 KB PDF) [3-5 months prior to close]
Word Document*(26 KB doc)
-
Conservation Plan (fully signed [3-5 months prior to close]
-
Forest Management Plan (FMP, if required) [2-3
months prior to close]


If environmental assessment yields negative
results - STOP. Further environmental evaluation will be required.

Step 7
Pre-Closing Continued
1 to 2 months prior to close
NRCS
performs the following task: Preliminary Title Opinion -- Review and closing - approval by
NRCS Assistant
State Conservationist for Programs
Entity submits the following documents within the requested time frame to
allow for NRCS review:
Step 5
Pre-Closing
4 to 12 months prior to close
Entity submits the following documents within the requested timeframe to
allow for NRCS review:
-
Survey [6-12 months prior to close]
(256 KB PDF)
-
Easement Deed Draft [5-12 months prior to close] (the Conservation Easement
Deed Template that will be used should be submitted within 30 days of signing the cooperative
agreement). NRCS recommends
using the approved
2012 Conservation Easement Deed Template
(waiting
for release from National Office)
-
Appraisal [4-12 months prior to close]
(187 KB PDF)
-
Preliminary Title Commitment Binder
(637 KB PDF) [4-12 months prior to close]
- ALTA Title Policy
- Exceptions and Encumbrances -- photocopy of each referenced document
- Chain of Title of fee ownership
- Draft Mortgage Subordination or Discharge (if applicable)





Step 9
Post-Closing Continued
1 to 3 months after close
Entity submits copies of the following
documents within the requested time frame to allow for
NRCS
review:
-
Recorded Conservation Easement Deed [1-3
months after close]
-
Final Title Commitment Binder [1-3 months
after close]
-
Closing Documents or
HUD statement
[1-3 months after close]
-
Signed Mortgage Subordination or Discharge
(if applicable) [1-3 months after close]
Once all post-closing documents are in,
NRCS
can process:
-
Advance of
Funds/Funds Reimbursement Form* (SF-270) (if an advance of
funds was not used) (42.5 KB xls)